Fully Permitted 9.6 MW / 25 MWh Stand-Alone Battery Storage (BESS) Portfolio

Fully Permitted 9.6 MW / 25 MWh Stand-Alone Battery Storage (BESS) Portfolio
Pays
ItalieItalie
ID de l’annonce
L#20261195
Prix cible
Prix sur demande
Chiffre d’affaires
À définir
EBITDA
À venir

Description

An opportunity to acquire 100% of the project rights and Special Purpose Vehicles (SPVs) holding a portfolio of three stand-alone Battery Energy Storage System (BESS) projects located in Piedmont, Northern Italy.

The aggregate portfolio represents 9.6 MW of nominal power and 25.0 MWh of storage capacity, strategically engineered to participate in wholesale energy arbitrage, capacity markets (MACSE), and ancillary grid services. All assets are fully permitted, grid-secured, and de-risked from real estate constraints.

Portfolio Breakdown & Technical Specifications

The opportunity can be acquired as a unified portfolio or structured via individual sub-projects:

Project Identifier Nominal Power (MW) Nominal Storage (MWh) Duration (C-Rate) Inverter (PCS) Setup Battery Units Grid Level Permitting Status Land Security

Project Alpha

4.8 MW

10.0 MWh

~2.1h (0.48C)

2 × 2.4 MW

2 × 5.0 MWh

Medium Voltage (MT)

Fully Permitted (PAS)

SPV-Owned Freehold

Project Beta

2.4 MW

10.0 MWh

~4.2h (0.24C)

1 × 2.4 MW

2 × 5.0 MWh

Medium Voltage (MT)

Fully Permitted (PAS)

SPV-Owned Freehold

Project Gamma

2.4 MW

5.0 MWh

~2.1h (0.48C)

1 × 2.4 MW

1 × 5.0 MWh

Medium Voltage (MT)

Fully Permitted (PAS)

SPV-Owned Freehold

Total Portfolio 9.6 MW 25.0 MWh 2.6h avg 4 × PCS units 5 × 5 MWh units

MT Grid

+ 2

100% PAS Authorized

+ 2

100% Freehold Owned

+ 2

Key Investment Highlights

Fully Authorized (RTB Stage)

All projects hold definitive authorization obtained via the simplified permitting procedure (PAS - Procedura Abilitativa Semplificata), including all associated administrative prescriptions.

Secured Grid Interconnection

Interconnection solution accepted at Medium Voltage (MT) with binding technical connection agreements (TICA accettata) formally in place.

Land Freehold Secured

The real estate plots are directly owned in fee simple by the project SPV(s), removing third-party lease risks, surface right expiries, or ongoing land rent charges.

Controlled Network Works Execution

Grid connection works can be executed directly by the project sponsor/buyer to ensure tight schedule supervision, direct supplier interfaces, and optimized energization timelines.

Engineering & Safety Compliance

Preliminary engineering layouts, single-line diagrams, perimeter security setbacks, and dedicated secondary emergency access routes compliant with Fire Department (Vigili del Fuoco) requirements have been incorporated into the project designs.

Transaction Structure & Process

  • Perimeter

    100% equity transfer of the clean corporate vehicles (SPVs) holding all authorizations, grid rights, land titles, and engineering documentation.

    Due Diligence Access

    Comprehensive Virtual Data Room (VDR) is established and accessible to qualified buyers upon execution of a standard Non-Disclosure Agreement (NDA).

    Pricing & Bidding

    The asset is offered without a fixed price expectation. Financial terms and pricing models are to be agreed upon through bilateral discussions and submitted via a non-binding indicative Term Sheet.

Informations clés

ID de l’annonce
L#20261195
Pays
Italie
Ville
Torino
Secteur
Énergie renouvelable
Statut de l’opération
Disponible
Prix cible
Prix sur demande
Chiffre d’affaires
À définir
EBITDA
À venir
Multiple de chiffre d’affaires
À définir
Multiple d’EBITDA
À définir

Conseil M&A mid-market – Deal Tombstones 2024

ConseillerDeals
MergersCorp M&A International21
Keith Advisory17
GCG9
JP Morgan41
Jefferies23
Lazard26
Goldman Sachs30

Entreprises à vendre

Opportunités similaires